The Mai Son-National Highway 45 expressway section has a total length of 63.37 km.
The bidding package No. 10 has a total length of 15,3km, connecting Mai Son commune in Yen Mo district of Ninh Binh province and Ha Long commune in Ha Trung district of Thanh Hoa province.
The section running through Ninh Binh province has a length of 14,35km. It is constructed by joint venture of Xuan Truong Construction Company and Son Hai Group.
According to thecontractor, currently, the cleared site for the project has been handed over to the contractor while an area of 3.4 hectares which wasadded to the project after adjusting Dong Giao intersection has been carried out compensation for site clearance.
To date, 76.14% of the workload has been completed with a total disbursed amount of over 1.3 trillion VND.
After his field trip and hearing the contractor's report, Thang spoke highly the drastic participation of the investor, contractors and Ninh Binh authorities.
The minister asked the investor and contractors to speed up the construction progress, striving to fulfill 100 percent of the workload before December 31, 2022, while ensuring the quality, technical and artistic factors of the project.